Order ORD-000338
Approved 2026-06-18 03:02 AM · Parselink · Air
Order Total
$49.56
Status
In Transit
Elapsed vs SOP
29.8d / 20d
SLA Breaches
4
Fulfilment
- Service
- Parselink
- Shipping
- Air
- Branch
- PP — Sen Sok
- Channel
- Agent
Status & Totals
- Status
- In Transit
- Approved at
- 2026-06-18 03:02 AM
- Last update
- 2026-06-18 03:02 AM
- Total
- $49.56
SOP Timeline — ORD-000338
Parselink · Air · PP — Sen Sok
Elapsed 29.8d / SOP 20d6 SLA breaches
Variance vs SOP: Early On SOP Internal Late
- Purchase Internal SolutionCompletedPurchase Team · SOP 1d · internal +1dStart: 2026-06-05 10:00End: 2026-06-06 22:00Actual 1.5dΔ +0.5d over SOP
- In Transit to WH China Internal SolutionCompletedPurchase Team · SOP 3d · internal +3dStart: 2026-06-06 22:00End: 2026-06-10 19:36Actual 3.9dΔ +0.9d over SOP
- Inbound WH China LateCompletedWarehouse China · SOP 3d · internal +3dStart: 2026-06-10 19:36End: 2026-06-17 00:24Actual 6.2dΔ +3.2d late · 0.2d past buffer
- Outbound Freight Internal SolutionCompletedLogistics · SOP 10d · internal +5dStart: 2026-06-17 00:24End: 2026-07-01 05:12Actual 14.2dΔ +4.2d over SOP
- Arrived at Destination OkayIn ProgressWH Hub PP · SOP 1d · internal +1dStart: 2026-07-01 05:12End: —Actual 1dΔ On SOP (0d)
- Shipping to Branch Internal SolutionPendingWH Hub PP · SOP 1d · internal +1dStart: 2026-07-02 05:12End: —Actual 1.4dAwaiting start
- Inbound WH Khmer Internal SolutionPendingInternal Warehouse · SOP 1d · internal +1dStart: 2026-07-03 14:48End: —Actual 1.6dAwaiting start